Shoreham Port

Mackley Construction are undertaking enabling works split over three sites at Shoreham Port.

sp01 sp02 spo03

The works consist of:

  • Approximately 22,000m² of block paving and associated ground leveling and preparation at the Fishersgate site.
  • 700m ducting for future lighting towers and other electrical installations.
  • Approximately 3,500m ³ of on site soil remediation
  • Two industrial units of 50m x 40m and 100m x 40m
  • New terminal entrance construction

This site uses a high quantity of recycled material with the majority coming from within the port itself.  Recycled slag from Holland is used as Type 1sub-base.   Much of the material need for site is transported by ship meaning only local delivery trips by road helping to reduce carbon emissions on the project.

Soil remediation is being undertaken on contaminated land on the site of an old power station to stop any contaminates leaching into ground water and surrounding areas.

Project: Shoreham Port